18 Nov - 24 Nov 2024
Rainfall (mm)
M
0.6
T
0.3
W
0
T
0
F
0
S
0
S
0
Incidents
40
0
P1.
38
P2.
2
P5.
Work timing
Ave. delay caused (seconds)
32s
Max delay caused
(seconds)
243s
Ave. time to start
(hours)
4.33hrs
Ave. time to complete (hours)
0.97hrs
Vehicle impact
Total vehicles through works
92,123
Total vehicle delay (minutes)
42,082min
Emissions caused (grams)
CO
59,617
NO
5,611
Economic cost
$53,699
25 Nov - 01 Dec 2024
Rainfall (mm)
M
0
T
0
W
0
T
3.3
F
2.3
S
4.2
S
0
Incidents
87
0
P1.
84
P2.
3
P5.
Work timing
Ave. delay caused (seconds)
42s
Max delay caused
(seconds)
388s
Ave. time to start
(hours)
4.27hrs
Ave. time to complete (hours)
1.24hrs
Vehicle impact
Total vehicles through works
118,737
Total vehicle delay (minutes)
71,453min
Emissions caused (grams)
CO
101,224
NO
9,527
Economic cost
$93,245